All revenue and profit are recognized after a project's completion
Over 1.8 million professionals use CFI to learn accounting, financial analysis, modeling and more. Start with a free account to explore 20+ always-free courses and hundreds of finance templates and cheat sheets.
The completed contract method of revenue recognition is a concept in accounting that refers to a method in which all of the revenue and profit associated with a project is recognized only after the completion of the project.
In addition to the completed contract method, another way to recognize revenue for a long-term contract is the percentage of completion method. The two revenue recognition methods are commonly seen in construction companies, engineering companies, and other businesses that mainly generate revenue on long-term contracts for projects.
Understanding the Completed Contract Method
The completed contract method defers all revenue and expense recognition until the contract is completed. The method is used when there is unpredictability in the collection of funds from the customer. It is simple to use, as it is easy to determine when a contract is complete. In addition, under the completed contract method, there is no need to estimate costs to complete a project – all costs are known at the completion of the project.
Journal Entries
Journal entries for the completed contract method are as follows:
Example
StrongBridges Ltd. was awarded a $20 million contract to build a bridge. The estimated time to complete the project is three (3) years with an estimated cost of $15 million. Assuming that the cost estimates do not change, the project is expected to generate $5 million in profit. The following is a schedule for the project using the alternate percentage of completion method:
Notes:
Costs Incurred are the costs incurred to build the bridge as estimated by the company’s engineer.
Billings is the amount of money StrongBridges Ltd. billed for the construction of the bridge. Billing amounts are set by the company.
Cash Collected is the amount of money StrongBridges Ltd. received for the construction of the bridge. The variation in billings and cash collected is due to timing differences.
% Completed is determined as costs incurred divided by estimated total costs.
For the completed contract method, revenue and expense are only recognized at the end of the contract. The journal entries are as follows:
Related Readings
CFI is the official provider of the global Financial Modeling & Valuation Analyst (FMVA)® certification program, designed to help anyone become a world-class financial analyst. To keep advancing your career, the additional CFI resources below will be useful:
Learn accounting fundamentals and how to read financial statements with CFI’s free online accounting classes.
These courses will give the confidence you need to perform world-class financial analyst work. Start now!
Building confidence in your accounting skills is easy with CFI courses! Enroll now for FREE to start advancing your career!
Take your learning and productivity to the next level with our Premium Templates.
Upgrading to a paid membership gives you access to our extensive collection of plug-and-play Templates designed to power your performance—as well as CFI's full course catalog and accredited Certification Programs.
Gain unlimited access to more than 250 productivity Templates, CFI's full course catalog and accredited Certification Programs, hundreds of resources, expert reviews and support, the chance to work with real-world finance and research tools, and more.